Dubai’s Mall of the Emirates to generate 3GWh from rooftop solar PV plant

The rooftop solar pv plant unveiled by Enova and Mall of the Emirates will lead to Dh1.4mn annual savings

Share
Spanning over 11,996 sqm, the plant is equivalent to the size of nearly two football fields
Spanning over 11,996 sqm, the plant is equivalent to the size of nearly two football fields

Dubai is accelerating the adoption of rooftop pv solar to generate clean energy and reduce power consumption costs.

Majid Al Futtaim, a leading shopping mall, communities, retail and leisure pioneer across the Middle East, Africa and Asia, recently unveiled the first phase of Mall of the Emirates’ solar photovoltaic (PV) plant.

The plant is set to generate 3 GWh of clean energy, saving up to Dh1.4mn on energy costs every year.

Led by Enova, the Middle East’s leading energy and facilities management specialist, a total of 7,291 photovoltaic panels were fitted to 1,068 carports.

Spanning over 11,996 sqm, the plant is equivalent to the size of nearly two football fields. The retrofit of the premises’ existing car park structure is a regional first.

Mall of the Emirates’ renewable energy plant brings Majid Al Futtaim one step closer to our commitment to become ‘Net Positive’ in carbon and water by 2040. This new solar PV plant is set to reduce 2,500 tonnes of carbon dioxide (CO2) emissions every year, equivalent to taking 480 cars off the road,” said Ibrahim Al'Zubi, Chief Sustainability Officer at Majid Al Futtaim-Holding.

The project is part of an initiative between Enova and Majid Al Futtaim’s Shopping Malls business unit to install solar PV to power three of its shopping malls by 2018.

The objective is to source a minimum of 7.5% of energy use on site via renewable energy at all new developments and a minimum of 5% in existing buildings.

“We encourage our clients to take a step further in their energy performance strategies by supporting them to not only implement energy conservation measures for increased energy efficiency, but also generate their own energy through on-site solar photovoltaic plants,” said Anne Le Guennec, Chief Executive Officer for Enova.

The work was completed in 10 weeks and the shopping centre remained fully operational throughout, resulting in minimal disruption to customers at one of the UAE’s busiest malls.