Mirfa IWPP goes into full commercial operation in Abu Dhabi

by Baset Asaba on Nov 8, 2017




Engie SA (ENGI.FR) has announced that the Mirfa Independent Water and Power Plant (IWPP) in Abu Dhabi is now into full commercial operation.

The 1,600 MW power and 52.5 million gallons (around 200,000 m3) per day (MIGD) seawater desalination capacity plant has the capacity to generate 10% of Abu Dhabi’s power requirements as peak capacity and over 5% of the emirate’s water generation.

The construction of the $1.5bn IWPP, located 160 kilometres away from Abu Dhabi, was initiated in October 2014. It is owned by ENGIE (20%), Abu Dhabi Water and Electricity Authority (ADWEA) (60%) and Abu Dhabi Financial Group (20%).

Developed under a full turn-key engineering, procurement and construction contract (EPC), the project integrates the acquisition of an existing 22.5 MIGD (85,000 m3 per day) water production facilities and associated infrastructure along with the acquisition, refurbishment, erection and commissioning of four GE 9E gas turbines with a combined net capacity of 360 MW acquired from the Al Mirfa Power Company.

In addition, the contract also covered the integration of a new 1,240 MW greenfield combined-cycle power generation plant and 30 MIGD (114,000 m3 per day) greenfield reverse osmosis desalination plant.

“Meeting the growing demand for electricity and water in the region, the Mirfa project is the tenth IWPP to be delivered in Abu Dhabi and the sixth ENGIE development project in the United Arab Emirates,” said Sébastien Arbola, CEO of ENGIE Middle East, South & Central Asia, and Turkey.

“Leveraging from our global expertise, we will continue to be a driver of smart energy solutions and are committed to working with our government and industry partners in the region to continue to meet their growing energy demands”, he added.

Following the commissioning, the plant will supply power and water services under a 25-year power and water purchase agreement (PWPA) with ADWEA as the single buyer. ENGIE will also be responsible for the delivery of operations and maintenance of the main plant for a 25-year period, in addition to the O&M services already provided to the other 5 ADWEA power and water desalination plants in the UAE: Al Taweelah A1, Shuweihat S1 and S2, Umm Al Nar and Fujairah F2.


FEATURED COMMENT

Please click here to comment on this article

COMMENTS

Name *
Email *
City
Country
Subject: *
Comments: *


  • LATEST NEWS

Informa_MEE_2017-small.jpg

Linkedin Page

LinkedIn

Sister websites:

Arabian Oil and Gas Middle East
Construction Week Online Middle East
Hotelier Middle East
Digital Production Middle East
Arabian Supply Chain Middle East

RELATED ARTICLES


NEWSLETTER SUBSCRIPTION

Official middle east partner to:

middle-east-electricity-logo

Articles
Companies